Open Mobility Semester Report: Fall 2024
Our Fall 2024 Report has been completed! The downloadable PDF is below. Open Mobility Fall ReportDownload
Our Fall 2024 Report has been completed! The downloadable PDF is below. Open Mobility Fall ReportDownload
Week of 9/9/24 . Project update 1. To Do list for the next week: Research everything since I am new and still need to learn about synthesizers MIDI compatibility and…
(9/13/2024) This week, I will be collaborating with my team to identify the necessary components for a dryer unit designed for the filament flip-flop system. This unit must function even…
OSHE (Deer Dissuader) Spring 2025: Project Update 12 (Apr. 20th) Final Project Image TO DO List Revise report draft Update the BOM Update Sponsorship Begin Preparing for next semester project…
(9/13/2024) This coming week I will be working on designing the general dryer unit for the filament flip-flop unit. This unit should work while the printer is off to ensure…
To Do : Discuss with BREAD the type of board we'll be using for the project. Determine the type of guide we should use for the filament in the rewind…
WEEK 4 - Project Update 3 Power sensing IC attached to breakout board Operational diagram PAST WEEK: Soldered the our system's primary IC, the power sensing module, to a breakout…
4/19/2025 Work Loag Reflection on work since last week Not a lot with exams coming up Project Report A bit of work on the report, added pictures and figures to…